70 PACIFIC ST.
Steel erection on the graduate housing project continues and may affect vehicular traffic.
CHEMISTRY BUILDING
Installation of replacement windows is in progress on all floors. There may be some disruption to occupants as offices and labs are moved.
STATA CENTER
Installation of formwork, reinforcing steel, embedded plumbing and electrical conduit continues.
VASSAR STREET UTILITIES
Trucking activity and machine work may limit parking and travel along Vassar Street.
LOBBY 7
To minimize the impact of the wet cleaning operation, work will take place from 4 p.m. to 2 a.m. Monday through Thursday.
BUILDINGS 16, 18 AND 26
To ensure safety during construction on the connection bridge, pedestrian traffic is being rerouted.
ZESIGER SPORTS AND FITNESS CENTER
Casting of columns is in progress. Construction activity may disrupt pedestrian and vehicular traffic and cause noise and some utility shutdowns.
SIMMONS HALL
Activity on Vassar Street may affect vehicular traffic.
Further information may be found at the Facilities web site.